Design qualification (DQ)
The long-term experience with pharmaceutical production equipment and facilities enables a fast and precise preparation of URS according to customer requests as well as FS in accordance with manufacturer information. The implementation of user requirements is also checked during design qualification.
The system functions are analyzed within a system-specific risk assessment. If necessary, additional qualification checks are defined. This enables an efficient definition of the qualification test scope.
Installation qualification (IQ)
The "as-built" status is compared with the specified requirements "as designed" during installation qualification (IQ). Based on clearly structured test sheets, the main equipment and the peripheral machines are checked on site for correct installation.
We verify process-critical parts, as well as the interfaces between media, upstream and downstream machines, and systems. The presence of technical documentation and certificates such as operating instructions and operating procedures, cleaning and maintenance requirements of the supplier, equipment drawings, calibration and material certificates, are also checked.
Operational qualification (OQ)
The operational qualification (OQ) is performed after the IQ and documents that the equipment can work without any failure within the defined acceptance criteria. The OQ test sheets are developed together with our customers regarding structure, content, and acceptance criteria according to the URS, the risk analysis, and the existing knowledge about processes, systems, and equipment.
Experienced Valicare validation engineers carry out the tests using our calibrated and qualified state-of-the-art measuring devices.
Performance qualification (PQ)
The performance qualification (PQ) shows the functionality and performance of the system under operating conditions. The test design and the acceptance criteria are developed according to customer requirements. The successfully executed tests demonstrate the performance of the entire system with all connected system components and complete the successful qualification.